Azerbaijan sheds light on Karabakh's energy supply progress

0
A 110/35/10 kV "Khankendi-1" substation and a 12 km double-circuit line were built for stable energy supply. Over 75 MW of hydropower plants were restored or built, including a 50 MW "Sarsang" plant. New 110 kV lines spanning 30 km connect key districts in the region.